757 Coastal Remodeling
757 Coastal RemodelingScope of Work & Estimate
Estimate #1397 · September 16, 2026
34 Roberta Dr, Hampton, VA 23666
$10,745.00Estimate — VA Repair Scope (revised)
34 Roberta Dr, Hampton, VA 23666
Repairs Cited in the VA Appraisal — MPR List
Print / Save PDF — Estimate #1397
Estimate valid until September 23, 2026
This scope covers the repair items listed in the VA appraisal report (VA-26-0085, effective 08/29/2026) for this property, plus the trades they carry. Anything outside that list is quoted separately — see Not Included. Masonry (10123) is pending a site measure and is quoted as its own number.
Project Overview
Customer
Lexie Ricci — LPT Realty
Project
VA repair scope — appraiser's cited MPR items
Property
34 Roberta Dr, Hampton, VA 23666
1964 ranch, 1,491 SF, crawl space
Appraisal
VA-26-0085 · effective 08/29/2026
Field Visit
Monday, September 14, 2026 — Jorge on site
Closing
This week — repairs are the loan conditions
Included Scope of Work
10101Trashout / Demolition
Removal and disposal of the replaced storm door, the burned electrical materials taken out at the HVAC disconnect, and the old HVAC equipment and materials removed during the change-out.
1 job
10109Doors & Trim
Safety egress repair (appraiser's item 1): remove the interior double-key deadbolt and install a single-key, thumb-turn deadbolt.
1 lock
10110Ext. Doors
Deteriorated exterior door (appraiser's item 3b): the damaged storm door at the family room is removed and a new storm door unit installed, weather-stripped and painted to match the existing exterior finish.
1 door
10121Electrical
Remove and replace the burned/damaged exterior HVAC disconnect. Inspect the HVAC branch-circuit conductors and connections for heat damage; replace damaged conductors, fittings, connectors and related electrical materials within the immediate HVAC disconnect area as necessary; replace the HVAC circuit breaker if damaged or compromised; reconnect the HVAC equipment and verify proper voltage and electrical operation after the repairs; secure and weatherproof the exterior electrical connections and remove debris associated with the repair.
1 system
10122HVAC
In-operable air conditioning (appraiser's item 2), licensed HVAC contractor: the existing R-22 unit is beyond repair, so it is replaced with a new complete system — the electrical connection to the unit restored, and the system started up and verified to safe and sound working order.
1 unit
10123Masonry
Cracked and separating brick (appraiser's item 4): grind out the deteriorated mortar along the cracked and separating joints in the brick veneer, then point up and re-grout with matching Type N mortar. Price pending — the mason measures on site and this work is quoted as its own number.
pending measure
Scope of Work Total$10,745.00
Itemized Estimate
ServiceQuantityPrice
10101 Trashout / Demolition
Haul-off and disposal of the replaced storm door, the burned electrical materials taken out at the HVAC disconnect, and the old HVAC equipment removed during the change-out.
1 job$295.00
10109 Doors & Trim
Safety egress: the interior double-key deadbolt is replaced with a single-key thumb-turn deadbolt.
1 lock$150.00
10110 Ext. Doors
The damaged storm door at the family room is replaced with a new storm door unit, weather-stripped and painted to match.
1 door$800.00
10121 Electrical
Burned exterior HVAC disconnect removed and replaced; HVAC branch-circuit conductors and connections inspected for heat damage and damaged conductors, fittings, connectors and materials replaced as necessary; HVAC circuit breaker replaced if damaged or compromised; equipment reconnected with voltage and operation verified; exterior connections secured and weatherproofed.
1 system$1,500.00
10122 HVAC
The existing R-22 unit is beyond repair and is replaced with a new complete system, started up and verified to safe and sound working order.
1 system$8,000.00
10123 Masonry
Cracked and separating joints in the brick veneer ground out, pointed up and re-grouted with matching mortar. Pending the mason's measure.
pending measurePending
Total
Masonry (10123) pending — quoted as its own number, not part of this total.
$10,745.00
Site Photos — Before Work
Payment Schedule
Deposit
50%
$5,372.50 — due upon acceptance, to schedule the trades
Final
50%
$5,372.50 — due upon completion
Terms & Clarifications

Scope: All work described in the Included Scope above. Any work not listed is not included unless agreed in writing. The scope follows the repair items cited in the VA appraisal for this property; items outside that list are quoted separately. The masonry (10123) point-up and re-grout is pending a site measure and is quoted as its own number — it is not part of the total above.

Structural excluded: header reinforcement, joist repairs, subfloor sheet replacement, engineering, foundation modifications.

Contractor supplies: the new storm door unit, the deadbolt, the electrical materials for the disconnect-area repairs, and the new HVAC system and materials.

MEP contingency: if live wiring or plumbing is found inside the wall, or further electrical damage is found once the burned box is opened, a change order covers the additional work before it proceeds.

Paint: the new storm door is painted to match the existing exterior finish as part of the installation. No other painting is included.

Notes: Jobsite will be left clean once completed. The completed repairs are the ones cited in the appraisal so the property can be re-inspected for the loan.

Warranty: 12 months workmanship.

Payment Terms: Total Project Cost $10,745.00 · Deposit to Schedule $5,372.50 · Final Payment $5,372.50. Check is a preferred method.
You can pay by credit card using the link below.
request.plastiq.com/pay-tidewater-home-improvement-llc
Cards not eligible for payment: Virtual Affirm credit card

Validity: one (1) week from the date above — valid until September 23, 2026.